2022-11-16
https://mp.weixin.qq.com/s?__biz=MzIyNzA4NTQ0Nw==&mid=2247488128&idx=1&sn=9f79452de8b25abaee53b305e95d8fd8&chksm=e867cf68df10467ea3b2c09299eadacb04c14628cebec162350e93011bfe2316fcbeb3c311aa#rd Read More
2022-09-16
Construction site:Jiangsu province, ChinaMaterial and specification of main pipe:900mm, PECrossing length:300mHDD machine Model:GS1000-LS Read More
2022-04-11
Project overview Read More
2021-11-13
Summary of large-scale HDD projects reports in October——Outstanding achievements of Goodeng’s customers, who have finished fifteen pipelines successfully. The customers of Goodeng Machinery have also reaped a fruitful harvest in October, which is a harvest month in China.They have completed their p Read More
2019-10-31
GOODENG MACHINE GS12000-T for Shandong XingRun National Energy Heating Project(⌀1422mm×1260m) GOODENG GS12000-T was sent to Shangdong Province, China On 21st Oct, to help finish the NationalEnergy Heating Project which is contracted by LiuBin engineering company. It is so exciting that Goode Read More
2019-10-01
1. Construction ProfileProject name:LNG subsidiary project Pipeline directional drilling crossing Phase IIProprietor / Development unit:CNOOC Eastern Guangdong Liquefied Natural Gas Co.,LtdConstruction unit: Henan Jinchang Petrochemical Construction Co., LtdProject characters:Rongjiang River Ф914mm* Read More
2019-08-24
I. Project Profile Project Name:China Petroleum and Chemical Corporation & Kuwait National Oil Company Limited Joint Project ---Zhanjiang, Lianjiang Product Oil Pipeline Project Sea Area HDD Works The Owner/Construction Party:China Petrochemical Marketing Co. Ltd -Huanan branch Construction Organiza Read More
2017-12-11
1.Project OverviewProject Name: outer net main line(power plant to bus terminal) Daqinggou Valley directional drilling and pipe pulling projectOwner Party: Henan Shangqiu Yudong Electricity Generating Co.,LtdConstruction Contractor: Shandong Wendeng Wantong Civil Engineering Co.,LtdProject Feature: Read More
2016-07-26
1、 Project profileThis project is CPC Corporation, Taiwan second natural gas pipeline, which reduces Taichung natural gas operation interruption risk, it mainly crosses Taichung port channel, steel pipe material, diameter Ø660mm, crossing length 1449m.Owner party: CPC Corporation, TaiwanConstructio Read More